Construction work to install the new cables and spare conduits is now complete. This involved trenching in streets between our substations in Kingsford and Randwick and boring under Alison Road, between the upper and lower sections of St Marks Road in Randwick.
Now that construction is finished, work is underway along the cable route to permanently restore traffic islands, roundabouts and pedestrian crossings impacted by the work. Permanent restoration of the impacted areas of roads is also underway, in consultation with Randwick City Council.
Work to retire the existing 132,000 volt cables between our substations in Waterloo and Randwick will begin in late 2019 and extend into 2020.
Ausgrid will keep residents, businesses and other stakeholders updated as the project progresses.