- Site investigations within and around the substation.
- Excavation works inside the zone substation to form a new cable basement.
- Construction of a switchroom building extension within the zone substation.
- Excavation and cable jointing works on the perimeter of the substation near Marigold Street to connect the new cables to the existing cables.
- The following equipment is anticipated to be used for the excavation and construction works: piling rig, excavators, jack hammers, trucks, front end loaders, mobile crane.
- Like any construction site, noise and dust may be generated and we will work to minimise these impacts and finish the work as quickly as possible.
The planned work will not disrupt your power supply.
Proposed timing and work hours
Excavation and construction works are expected to begin in [date] and will take approximately [x] months to complete.
Construction hours would be between 7.00am and 6.00pm, Monday to Friday, and 8.00am and 1.00pm on Saturdays, unless otherwise advised. Please note that Ausgrid will liaise with adjoining land occupiers well in advance of any work commencing.
Equipping works inside the substation would follow however will be primarily undertaken within the new building.