*calculations are based on a 20kWh/100km vehicle energy usage
For more information on electric vehicle charging visit Transport NSW website - 'Electric Vehicles'.
Vehicle to Grid (V2G)
Vehicle to Grid (V2G) is an overarching term for technology that can enable electricity to be exported from the battery of an electric vehicle (EV) to a home, building or the electricity network. Only a small number of EV models and EV Chargers are V2G-capable in Australia. This is expected to increase as the technology becomes more advanced from around 2025.
As this remains an emerging technology, the availability of V2G-capable vehicles and V2G-capable EV Supply Equipment (EVSE) remains low. Where new V2G-capable EVSE products become available, they will need to be compatible with your EV and must be compliant with the Australian Standards and Ausgrid’s Connection Standards.
We advise to check with your EV charger supplier to find out if their product meets the Australian Standards.
EV charging locations
Check the Electric Vehicle Council EV charger map for proposed and existing EV charging sites.
Installing an EV charger for your home or business
Consider the following before installing EV charging:
- Do your research and get multiple quotes from different EV charging and installation providers.
- A licensed electrician will review your requirements and the electrical wiring at your premises to advise you about any work that could be required as part of the installation.
- If your home is over 20 years old and has not been rewired, you may need to upgrade your existing meter to ensure usage information is captured accurately for billing. Your electricity retailer is responsible for any changes to your metering or electricity retail tariff.
Read more about metering on the AEMC’s website.
- If you are considering installing an EV charger in an apartment or multi-tenanted property, find out more about strata and apartment considerations on the Energy NSW website 'Making your strata building EV Ready'.
If a connection application is required to modify or upgrade your connection
In some instances, Ausgrid's approval is required where your licensed electrician has identified the need to upgrade the supply to your premises. In this case, a connection application is required for Ausgrid to assess any impacts of additional load on the distribution network. For further information, please visit ‘Apply for a Connection’ and choose the application that meets your requirements. We recommend that your licensed electrician completes the connection application form on your behalf.
Information for stratas considering EV charging
From October 2023, changes made to the National Construction Code (NCC) will require new apartment buildings to ensure the provision of base infrastructure for EV charging, including future cabling needs and control-point installation at the time of construction.
For existing apartment buildings, apartment owners and strata schemes should consider their high-level EV charging needs in consultation with all residents and the strata committee. The NSW government has provided information and advice to support the residential strata building community. This outlines stakeholder responsibilities, recommended steps to start planning for EV charging needs and an overview of the different types of solutions which will need to consider the various needs and circumstances of the building and residents. More information can be found on the Energy NSW website.
You will need to engage an electrical contractor to recommend the most suitable options for your building and residents needs. If required, they can submit a preliminary enquiry to Ausgrid to determine the connection capacity for the building.
Information for commercial businesses considering EV charging
It is the building owners responsibility to manage the installation of EV charging. Commercial building owners should consider:
- The tenants' charging requirements (short day charging, vs. overnight) and how many chargers will be required for this purpose
- How tenants will pay for charging
- Will demand for EV charging increase in future
- If fast charging is required, what works are needed
EV fleet incentive
Grants are available for for eligible NSW organisations to support the transition to EV fleets and smart charging infrastructure conversion. Find out more.
Electric vehicle fast charging grants
Grants are also available for installation of chargers at commercial businesses in regional NSW. Read more about NSW Government’s regional business EV charger incentives.
More information
Energy NSW provides information on considerations for commercial buildings looking to install EV charging facilities. Refer to the Energy NSW Commercial Building Factsheet.
Partnership opportunities
Ausgrid is partnering with commercial operators to provide ‘close to home’ EV charging by utilising our substations and poles. Read more about our partnerships.
Nominate a charging location
Are you interested in nominating a new EV charging location in Ausgrid's network area? We welcome nominations from councils, customers, and third parties for kiosk and kerbside pole-mounted charging. Nominate a charging location.